Stages of Cost Estimating
STAGES
OF COST ESTIMATING
1.
Briefing / Feasibility Stage
Two types of costing are
dealt with at this stage namely:
a. Cost of conducting feasibility studies b. Cost estimate of the whole planned or proposed project including (a) above.
a. Cost of conducting feasibility studies b. Cost estimate of the whole planned or proposed project including (a) above.
- Cost Estimate for conducting Feasibility Studies when the work is to be done by the Ministry, Regional or District Water Department, or Water Authority. Main components are:-
a. a . Manpower:
i.
Skilled allowance / night
ii.
Unskilled allowance / night
iii. Laborers daily pay
b.
Tools / Equipment: to be specified
c.
Transport: Hire and fare charges or oil, lubricant and minor
repair when transport is provides by the office.
d.
Preparation of Report: This is a lump sum cost of stationeries,
lunch allowances, etc.
e.
Contingencies @ 15%.
- When feasibility studies and designs are to be done by a consulting firm his cost estimate shall be prepared according to Terms of Reference for the project.
2.
Preliminary Design Stage
At this stage a fully
picture of the project is perceived. Cost estimates are often done against
major components.
For a Water Supply Project
for Example:
Construction Works
Ø Mobilization
– lump sum
Ø Intake
structure – lump sum
Ø Suction
pipe (…. m long) - lump sum
Ø Pumping
station (if any)
Ø Water
treatment (if any) - lump sum
Ø Sump
(…..m3) - lump sum
Ø Pump
house (if any) - lump sum
Ø Raising
main / gravity main (…m long) - lump sum
Ø Reservoir
(…m3) - lump sum
Ø Distribution
mains (….m long) - lump sum
Attendants quarters (…. m2) - lump sum
Operation and Maintenance
costs
Ø Administration
costs - lump sum
Ø Chemicals
- lump sum
Ø Manpower
- lump sum
Ø Cost of repairs and servicing of material equipment - lump sum
An alternative is to develop cost curves for each
major element of a project in which cost is plotted against size or volume. The
appropriate cost can then be quickly read off. However it does require a
sufficient number of recent historic examples brought to a present cost value
to develop such curves and is therefore more likely to be a costing tool
available to a firm of consultants.
3.
Detailed
Design and Preparation of Tender Dossier Stage
Preparation of
tender documents shall be done if and only if the project is to be executed by
a contractor. For this reason, a tender dossier shall be prepared according to
the constitutions of contract procedures. Specifications and bill of quantities
of the tender dossier shall be prepared in accordance with the detailed designs
of the project, the quantity survey and the Method of Measurement opted for.
Based on the detailed designs, major components in item 8.3.2 above are split
into classes, and divisions or minor items to allow for identification of
required materials and more accurate cost estimate of the project.
A cost estimate
for borehole drilling and measurement of general construction items are worked
as follows:-
(a) Cost estimate
for borehole drilling
(b) Measurement of
general construction items,
and can follow the following layout:
COST
ESTIMATE
FOR BOREHOLE DRILLING
COST ESTIMATE FOR
BOREHOLE DRILLING
Item Description
|
Unit
|
|
1
|
Mobilization and
Demobilization
|
Lump sum
|
2
|
Drilling
|
m
|
3
|
Drilling mud
(bentonite & cement)
|
Lump sum
|
4
|
PVC casings
|
m
|
5
|
PVC screen
|
m
|
6
|
Gravel
|
m3
|
7
|
Installation of PVC pipes, Screen and gravel
|
Hr
|
8
|
Development and cleaning
|
Hr
|
9
|
Pump test for 24hrs
|
Hr
|
10
|
Sub total
|
|
Add 30% for replacement of equipment
|
||
Add 30% for labour wages, inspection
and allowance to driller
|
||
Add 10% for contingencies
|
||
GRAND TOTAL
|
Preliminary
and General Items
Preliminary
and General Items can be included in a Cost Estimate as a % of the total
Construction Costs in which case it is recommended that 14% be added onto to
the estimated Construction Costs.
In the
Bills of Quantities, two methods are possible, the preferred one being to
include a totally separate Bill, Bill One for this purpose. This then enables a
clear costing to be established and understood and provides both Client and
Contractor with a clear understanding of what is expected and when. The
alternative, which is not recommended is to provider a detailed list of
requirements and then get Bidders to spread these costs throughout the Works
items. Unfortunately this seemingly simple method then often results in
disputes, especially where the scope of works changes or there are time
over-runs that are beyond the Contractor to control.
Estimating
and Including the Cost of Labour
In some
cases labour is taken as percentage (% age) of cost of materials (i.e. 20-30%).
This method is used but it gives a rough estimate because there are some
materials which have very high price but need very little labour to fix in
position (e.g. water pumps, etc.) Some items do not have materials to be
purchased but need only labour (e.g. excavation). The best method is to
identify manpower required at each category (e.g. skilled, unskilled etc.) for
each item for a specified period. Labour productivity is essential for
estimation of man-days. Total man-days of each category is incorporated as a
cost into the bill of quantities cost estimate as deemed most appropriate.-
Estimating
and Including the Cost of Transport
Cost of transport shall be worked out in accordance with
established hiring rates within the area concerned and again incorporated into
the bill of quantities cost estimate as deemed most appropriate.
No comments